STEEL REPAIR PROJECT BEGINS ON CURTIS CREEKDRAWBRIDGE APPROACH SPANS

BALTIMORE, MD - The MD Transportation Authority (MDTA) announces a $1.5 million project to perform steel girder repairs to the approach spans of the I-695 drawbridge over Curtis Creek, between Quarantine Road (Exit 1) and MD 10 (Exit 2), beginning this month.  This preservation project, anticipated to last approximately six months and funded completely by toll revenue, is part of the MDTAs commitment to preserving and maintaining the States aging toll bridges, tunnels and highways.

Construction includes repairs to the steel girders (structural steel) on the approach spans, the areas on either side of the main drawbridge section.  Contractor Joseph B. Fay Company of Baltimore will also clean and paint the structural steel of the repaired areas.

Single-lane closures may be in effect on the INNER LOOP and OUTER LOOP of I-695 during the following off-peak hours: daily from 9 a.m. to 3 p.m. and Sunday through Friday from 9 p.m. to 5 a.m. the following morning.  No closures are permitted the day of, preceding or following a major holiday.

The INNER LOOP of the I-695 Curtis Creek Drawbridge (one-lane of traffic in each direction) was opened when the Francis Scott Key Bridge opened in 1977.  The OUTER LOOP drawbridge span was added in 1979, resulting in two lanes of travel in each direction.  The current deck replacement project on the Curtis Creek drawbridge, which began last January, is nearing completion this month.

Portable and overhead electronic message signs will display travel information.  For information on the MDTA's other facility preservation projects, or to view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  For statewide travel conditions, visit MD511.ORG or call 511.  Follow TheMDTA on Twitter. 

The MDTA thanks its customers for their patience and reminds them to Stay Alert So No One Gets Hurt!!

FOR IMMEDIATE RELEASE

June 7, 2012

Contact:          Cheryl Sparks or John Sales

                        410-537-1017

AVOID I-895 & THE BALTIMORE HARBOR TUNNEL THIS SUMMER **MAJOR DELAYS EXPECTED**
K-Truss Steel Bridge Repairs South of Tunnel with 24/7 Lane Closures; Use I-95 and I-695/Key Bridge Instead

BALTIMORE, MD – Necessary work to preserve and resurface the 55-year-old “K-Truss” steel bridge deck on I-895 south of the Baltimore Harbor Tunnel will lead to major congestion and delays for drivers who choose to travel the route this summer.   The nearly $5 million project, funded completely by toll revenue, requires an eight-week duration of continuous (24/7) single lane closures on I-895 beginning on or about June 20, with major delays anticipated.

“Our message is very clear – avoid I-895 this summer and instead use the Fort McHenry Tunnel on I-95 or the Key Bridge on I-695.  If you drive I-895, expect major delays, especially during rush hours, potentially as much as 60 minutes per trip,” said MD Transportation Authority (MDTA) Executive Secretary Harold M. Bartlett.  “This concrete work simply cannot be done while keeping all lanes of I-895 open.  Our team developed a complex sequencing of construction and traffic patterns that will accomplish the work while still keeping at least one lane of I-895 open in each direction over the eight-week period.  I thank our customers for their patience, understanding and willingness to adjust their travel habits.”

In addition to weekday rush hours, major delays are expected Saturdays beginning around noon on southbound I-895 and Sundays beginning around 4 p.m. on northbound I-895.

Through extensive sampling and testing of the concrete, the MDTA confirmed that it is necessary to perform a milling and resurfacing of the top 3.5 inches of the K-Truss bridge deck using Latex Modified Concrete.  Construction includes removing and replacing portions of the existing concrete-filled steel grid bridge deck, removing and reconstructing portions of the existing concrete and steel median barriers, and performing drainage improvements.

The work zone consists of the I-895 K-Truss bridge and approach roadways between Exit 8 (Shell Road/Hanover Street) and Exit 7 (Potee Street).  Median barrier work will also be performed on I-895 over Frankfurst Avenue.  Scheduled to be complete in October 2012, work will be performed in four stages.   

  • Stage 1 beginning on or about June 20 (approximately 30 days): one northbound lane closed (left lane) and two southbound lanes open.
  • Stage 2 beginning mid-July (approx. two weeks): one northbound lane closed (right lane) and two southbound lanes open.
  • Stage 3 beginning early August (approx. two weeks): two southbound lanes closed with two-way traffic -- one lane for northbound traffic and one lane for southbound traffic -- on northbound bridge.
  • Stage 4 beginning mid-August (approx. 45 days): both lanes open in each direction with traffic shifted to outside lanes for work in center median.  Reduced lane widths on I-895.  No work will be performed during the Labor Day holiday weekend and the Baltimore Grand Prix.

The schedule is subject to change due to weather and other variables.  Additional off-peak lane closures will occur as necessary.

This current deck rehabilitation project is being performed by Eastern Highway Specialists, Inc., of Wilmington, Del.  The K-Truss bridge deck was last resurfaced in 2000.  This minor project included a less extensive rehabilitation of the deck using limited, short-term lane closures.   

Other preservation projects expected to begin on I-895 this summer include a deck replacement project on the I-895 bridges over Patapsco Avenue, Potee Street and Hanover Street, a resurfacing project for the ramp from northbound I-97 to northbound I-895 and a cleaning and painting project for 11 bridges along I-895.  In addition, a cleaning and painting project is underway for five bridges south of the Baltimore Harbor Tunnel.  

Motorists should be aware of portable and overhead electronic message signs that will display closure and/or detour information.  For information on the MDTA’s other facility preservation projects, or to view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  For statewide travel conditions, visit MD511.ORG or call 511. 

The MDTA thanks its customers for their patience and reminds them to Stay Alert So No One Gets Hurt!!