(I-695) CURTIS CREEK DRAWBRIDGE OPENINGS SCHEDULED FOR OCT. 9 - 12, 2013

The (I-695) Curtis Creek Drawbridge will open for U.S. Coast Guard water traffic on Oct. 9 - 12, 2013.  Drawbridge will remain open until water traffic passes beneath.

DRAWBRIDGE SCHEDULE:

  1. Wednesday, Oct. 9 - 9 a.m. and 6 p.m.
  2. Thursday, Oct. 10 - 9 a.m.
  3. Friday, Oct. 11 -  2 p.m.
  4. Saturday, Oct. 12 - 11:45 a.m.

 