FOR IMMEDIATE RELEASE

Dec. 16, 2013

Contact:          Tamory Winfield

 410-537-1017

 

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE

(US 40) UNDERWATER REPAIRS ON DEC. 18

Work to result in construction-related noise and additional truck traffic

  

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  The truck route is as follows:  Westbound US 40, to Otsego Street, to Water Street.

WHEN:           Wednesday, Dec. 18, from 7 a.m. to 10 p.m.  In the event of inclement weather or other variables, work also may be performed Thursday, Dec. 19.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

 

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information. 

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

 

###

 

FOR IMMEDIATE RELEASE

Oct. 30, 2013

Contact:          Tamory Winfield

 410-537-1017

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON NOV. 2

Work to result in construction-related noise and additional truck traffic

 

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  The truck route is as follows: I-95 to MD 222(Perryville Road), to U.S. 40, to Coudon Boulevard, to MD 7 (Philadelphia Road), to Roundhouse Drive.

WHEN:           Saturday, Nov. 2, from 5 a.m. to 5 p.m.  In the event of inclement weather or other variables, work also may be performed Saturday, Nov. 9.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

 

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

 

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

 

###

FOR IMMEDIATE RELEASE

Sept. 5, 2013

Contact:          Tamory Winfield

 410-537-1017

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON SEPT. 7

Work to result in construction-related noise and additional truck traffic

 

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  The truck route is as follows:   I-95 to MD 222 (Perryville Road), to U.S. 40, to Coudon Boulevard, to MD 7 (Philadelphia Road), to Roundhouse Drive.

WHEN:           Saturday, Sept. 7, from 5 a.m. to 5 p.m.  In the event of inclement weather or other variables, work also may be performed Saturday, Sept. 14.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

 

###

 

FOR IMMEDIATE RELEASE

August 7, 2013

Contact:          Tamory Winfield

 410-537-1017

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON AUGUST 9

Work to result in construction-related noise and additional truck traffic

 

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  Perryville Road), to U.S. 40, to Coudon Boulevard, to MD 7 (Philadelphia Road), to Roundhouse Drive.

WHEN:           Friday, August 9, from 4 a.m. to 3 p.m.  In the event of inclement weather or other variables, work also may be performed Monday, August 12.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

 

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

 

                                                                                  ###

FOR IMMEDIATE RELEASE

July 9, 2013

Contact:          Tamory Winfield

 410-537-1017

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON JULY 13 - 14

Work to result in construction-related noise and additional truck traffic

 

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  Perryville Road), to U.S. 40, to Coudon Boulevard, to MD 7 (Philadelphia Road), to Roundhouse Drive.

WHEN:           Saturday, July 13, from 6 a.m. to 3 p.m. Sunday, July 14.  In the event of inclement weather or other variables, work also may be performed Saturday, July 20 through Sunday, July 21.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

 

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

 

                                                                                 ###

FOR IMMEDIATE RELEASE

June 5, 2013

Contact:          Tamory Winfield

 410-537-1017

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON JUNE 8 - 9

Work to result in construction-related noise and additional truck traffic

 

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  The truck route is as follows:  Westbound US 40, to Otsego Street, to Water Street.

WHEN:           Saturday, June 8, from 6 a.m. to 3 p.m. Sunday, June 9.  In the event of inclement weather or other variables, work also may be performed Saturday, June 15 through Sunday, June 16.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

###


 

FOR IMMEDIATE RELEASE

May 15, 2013

Contact:          Tamory Winfield

 410-537-1017

 

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON MAY 18 - 19

Work to result in construction-related noise and additional truck traffic

 

WHAT:           The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  The truck route is as follows:  Westbound US 40, to Otsego Street, to Water Street.

WHEN:           Saturday, May 18, from 6 a.m. to 3 p.m. Sunday, May 19.  In the event of inclement weather or other variables, work also may be performed Wednesday, May 22 through Thursday, May 23.

WHY:              Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers.

 

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

 

                                                                                        ###

FOR IMMEDIATE RELEASE

March 19, 2013

Contact:         John Sales

                        410-537-1017

CONCRETE POURS SCHEDULED FOR HATEM BRIDGE (US 40) UNDERWATER REPAIRS ON MARCH 21
Work to result in construction-related noise and additional truck traffic

WHAT:  The Maryland Transportation Authority (MDTA) has scheduled concrete pours for foundation repair work on the Thomas J. Hatem Memorial Bridge (US 40) in Harford and Cecil counties. Nearby residents, motorists, business owners and their customers may experience higher than normal levels of construction-related noise and additional truck traffic during this time.  The truck route is as follows: Westbound US 40, to Otsego Street, to Water Street.

WHEN:  Thursday, March 21, from 7:00 a.m. to 6:00 p.m.  In the event of inclement weather or other variables, work also may be performed Friday, March 22.   This is the first scheduled concrete pour with three additional pours to follow over the next two months.

WHY:  Work is part of a preservation project to perform underwater foundation (concrete piers/bridge supports) repairs to the Hatem Bridge and is necessary to secure the structural integrity of the bridge piers. 

The nearly $48 million project is anticipated to be complete by fall 2014.  A similar project to perform underwater foundation and substructure repairs to the Millard E. Tydings Memorial Bridge on the John F. Kennedy Memorial Highway (Interstate 95) began in October 2011.

To view real-time traffic camera images on MDTA roadways, visit mdta.maryland.gov.  Know Before You Go!  Call 511 or visit MD511.org for statewide travel information.

Follow the MDTA at twitter.com/TheMDTA and facebook.com/TheMDTA.

The MDTA thanks motorists for their patience.

###

FOR IMMEDIATE RELEASE

January 1, 2013

Fracility: (US 40) Thomas J. Hatem Memorial Bridge

(US 40) HATEM BRIDGE - NO TRAFFIC ADVISORIES AT THIS TIME

There are no traffic advisories at this time.  In the event of a traffic advisory, important news and information concerning the Hatem Bridge will be posted to this blog.